期刊文献+

地铁车站顶部龙门吊轨道基础设计计算 被引量:5

DESIGN CALCULATION OF TRACK FOUNDATION FOR GANTRY CRANE LOCATED AT THE TOP OF A SUBWAY STATION
在线阅读 下载PDF
导出
摘要 某地铁车站为一地下两层的钢筋混凝土结构 ,车站顶板横向净跨距 16 3m ,厚度 0 8m ,顶板下无梁无柱 ,其上覆盖一层 1 2m厚的人工填土。车站顶板上方地表沿车站纵轴方向平行布置了两台重型龙门吊 ,龙门吊的一条轨道基础铺设在车站顶板跨中上方的填土层上。通过分析研究并采取了相应的措施 。 A certain subway station is a two storey reinforced concrete structure. The transverse clear span and thickness of the top plate of the station are 16 3 m and 0 8 m respectively; there are no any beams and columns below the top plate that is covered with an artificial fill (1 2 m). Two heavy duty gantry cranes are arranged along the longitudinal shaft of the station at the surface above the top plate, and the foundation for one track of the cranes is laid on the fill above the top plate′s midspan. Therefore, the problem to be solved by the design of the track foundation is how to ensure that the load of the top plate due to the wheel pressure of the cranes is less than that permitted by the top plate.
出处 《工业建筑》 CSCD 北大核心 2003年第1期79-81,共3页 Industrial Construction
关键词 地铁车站 龙门吊 轨道 基础设计 计算 钢筋混凝土结构 盾构施工 station\ gantry crane\ track\ foundation\ design
  • 相关文献

参考文献1

  • 1张岐宣.混凝土结构设计--基本理论、方法和实例[M].南京:江苏科学技术出版社,1993.202-212.

同被引文献30

引证文献5

二级引证文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部