期刊文献+

高扬程水泵站初扬水充水系统的设计 被引量:1

Design of the pre-filling water system for high lift pump stations
在线阅读 下载PDF
导出
摘要 高扬程水泵站在初次投入运行时对出水系统需要充水。针对充水系统运行扬程变幅大、运行条件恶劣 ,但使用时间短、系统利用率较低的特点 ,从充水方案的确定、充水设备的选择及运行等方面作了分析研究。山西省万家寨引黄工程水泵站的初扬水充水系统的设计和运行情况实践 ,可供今后其他工程设计参考。 The water outlet system of high lift pump station has to be pre filled water before it is put into initial commissioning. This article explains in detail the research results on alternative establishing about filling water system, selection and operation about equipment, specially for large variation range of operating lift, the worst operating conditions, the short time use, and lower utility factor etc. More experience, relative to design and operation of pre filling water system in the Wanjiazhai Water Diversion Project from the Yellow River in Shanxi Province, could be available for reference to other projects in the future.
出处 《水力发电》 北大核心 2003年第1期47-50,共4页 Water Power
关键词 高扬程 水泵站 初扬水 充水设计 万家寨引黄工程 water filling design, high lift, pump stations, pre filling water, Wajiazhai Water Diversion Project from the Yellow River
  • 相关文献

同被引文献1

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部