本文通过对上海市轨道交通13号线东延伸工程高科中路站~丹桂路站盾构区间废弃燃气钢管的拔管清障方案研究,为区间障碍物清理提供了除全回转清障方案以外的清障方式,为类似工况的清障提供借鉴。
This paper presents a research on the pipe pulling and obstacle removal scheme for the abandoned gas steel pipes in the shield tunneling section between Gaoke Middle Road Station and Dangui Road Station of the East Extension Project of Shanghai Rail Transit Line 13.It provides an alternative obstacle removal method to the full-rotation obstacle removal scheme for the section's obstacle clearance,offering references for similar working conditions.
作者
张军
ZHANG Jun(Shanghai Tunnel Engineering Co.,Ltd.,Shanghai 200082,China)
出处
《价值工程》
2026年第6期118-120,共3页
Value Engineering
关键词
盾构区间
废弃钢管
清障
拔管
shield tunneling section
abandoned steel pipes
obstacle removal
pipe pulling