基于大型水利枢纽船闸金属结构布置方案,闸门(阀门)及启闭设备布置选型,笔者从技术、运行和投资等方面,对上闸首闸门挡洪方案和上、下闸首检修闸门启闭及存储方案进行比选;介绍闸门(阀门)启闭系统、船闸浮式系船柱、防撞警戒装置的选用和布置。
Based on the layout scheme of metal structure of shiplocks in large hydro project the layout and selection of gate valve and hoisting equipment the authors compare and select the flood retaining scheme of upper lock head gate and the opening and closing and storage scheme of upper and lower lock head maintenance gate from the aspects of technology operation and investment.The selection and arrangement of gate valve hoisting system floating mooring column of shiplocks and anti-collision warning device are introduced.
作者
李鹏博
招滨
张学东
LI Pengbo;ZHAO Bin;ZHANG Xuedong(China Energy Engineering Group Guangxi Electric Power Design Institute Co.Ltd.,Nanning 53007 China)
出处
《红水河》
2024年第6期36-40,共5页
关键词
二线船闸
闸门
启闭机
西津水利枢纽
second-line shiplocks
gate
hoist
Xijin Hydro Project