东滩煤矿3308综放工作面过断层破碎带技术及安全措施研究 被引量:8

Research on Technology and Safety Measures of 3308 Fully Mechanized Caving Face Passing Fault Fracture Zone in Dongtan Coal Mine
在线阅读 下载PDF
导出
摘要 为解决复杂条件影响下工作面过断层破碎带问题,以东滩煤矿3308综放工作面为工程背景,基于现场复杂工程条件及设备条件,综合考虑巷道加固方式、超高区段装顶改造方式、采煤机截割层位控制等方面,设计制定了合理的工作面过断层破碎带方案,并成功应用于现场,有效的保障了工作面正常回采,提高了煤炭资源回收率。 In order to solve the problem that the working face passes through the fault fracture zone under the influence of complex conditions,the 3308 fully mechanized top coal caving working face of Dongtan Coal Mine is taken as the engineering background,based on the complex engineering conditions and equipment conditions on site,and comprehensively considering the roadway reinforcement mode,the superelevation section roof installation and transformation mode,the shearer cutting layer control and other aspects,a reasonable working face passing through the fault fracture zone scheme is designed and formulated,and successfully applied to the site,effectively ensuring the normal mining of the working face,Improve the recovery rate of coal resources.
作者 冯冉 FENG Ran(Dongtan Coal Mine,Yankuang Energy Group Co.,Ltd,Zoucheng 273500,China)
出处 《煤矿现代化》 2023年第5期1-5,共5页 Coal Mine Modernization
关键词 断层破碎带 超前提刀 资源回收 fault fracture zone advance knife lifting resource recycling
  • 相关文献

参考文献5

二级参考文献11

共引文献10

同被引文献60

引证文献8

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部