摘要
以目前世界最高沥青混凝土心墙堆石坝——去学水电站施工实践为依托,根据心墙的设计特点,通过对配合比进行的试验比选和现场施工实践数据分析,对沥青混凝土的施工参数进行了选择和优化,对高质量、高效率进行沥青混凝土心墙施工起到了指导作用,取得了较好的效果。
Relying on the construction practice of the world's highest rockfill dam with asphalt concrete core wall of Quxue Hydropower Station,this paper selects and optimizes the construction parameters of asphalt concrete according to the design characteristics of the core wall through experimental test of the mix ratio and analysis of the field data,which plays a guiding role in construction of high-quality and high-efficiency asphalt concrete core wall,and good results are achieved.
作者
廖果
LIAO Guo(Third Branch of Sinohydro Bureau 7 Co., LTD, Chengdu, Sichuan, 610213)
出处
《四川水力发电》
2021年第6期47-49,73,共4页
Sichuan Hydropower
关键词
去学水电站
沥青混凝土
参数优化
试验研究
Quxue Hydropower Station
asphalt concrete
parameter optimization
experimental study