先开挖后施工预制工程桩工法在舟山软土基坑中的应用 被引量:1

Application of Precast Pile Method of Excavation Before Construction in Zhoushan Soft Soil Foundation Pit
在线阅读 下载PDF
导出
摘要 依托工程实例,介绍了新型先开挖后施工预制工程桩工法在舟山地区软土基坑中的应用情况。通过采取关键技术措施,该工法可以解决软土基坑开挖对预制工程桩的影响问题。通过对现场实际开挖情况及现场实时监测数据的研究,证明该工法在软土地区具有可行性和使用价值,在一定条件下可选取该工法以降低工程桩费用。 Based on an engineering example,the application of precast pile method of excavation before construction in Zhoushan soft soil foundation pit is introduced.By taking key technical measures,this method can solve the influence of soft soil foundation pit excavation on precast engineering piles.The research on the actual excavation and onsite real-time monitoring data proves that the construction method is feasible and valuable in soft soil areas.Under certain conditions,the construction method can be selected to reduce the cost of engineering piles.
作者 朱国权 周韬 王乾浩 ZHU Guoquan;ZHOU Tao;WANG Qianhao(Zhejiang Geological Prospecting Institute of CCGMB,Hangzhou,Zhejiang 310002,China;Ningbo University Foundation Treatment Technology Co.,Ltd.,Ningbo,Zhejiang 315211,China;Zhejiang Hongchen Construction Co.,Ltd.,Ningbo,Zhejiang 315032,China)
出处 《建筑施工》 2021年第10期2016-2018,共3页 Building Construction
关键词 先开挖后打桩 软土基坑 换填层 监测分析 excavation before piling soft soil foundation pit replacement of filled layer monitoring analysis
  • 相关文献

参考文献3

二级参考文献9

共引文献13

同被引文献18

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部