摘要
针对陕西彬长文家坡矿业有限公司4106工作面运输顺槽巷道变形严重问题,设计采用锚杆+金属网/塑钢网+W钢带+锚索联合支护方案。在顺槽内布置2个测站,监测结果表明:巷道围岩顶底板和两帮变形量得到有效控制,支护效果良好。
Aiming at the serious deformation problem of transportation roadway in the 4106 working face of Shanxi Binchang Wenjiapo Mining,the combined support scheme of bolt+metal mesh/plastic steel mesh+W steel belt+anchor cable is adopted.The monitoring results show that the deformation of roof,floor and two sides of roadway surrounding rock is effectively controlled,and the supporting effect is good.
作者
陈泽年
王树明
Chen Zenian;Wang Shuming(Shaanxi Binchang Wenjiapo Mining Co.,Ltd.,Shaanxi Binzhou 713500)
出处
《山东煤炭科技》
2021年第2期85-86,共2页
Shandong Coal Science and Technology
关键词
顺槽
支护
研究
channels
support
research