北京地铁暗挖车站边桩止水方法比选研究 被引量:4

COMPARISON AND SELECTION OF SIDE PILE WATER-STOP METHODS FOR BEIJING SUBWAY STATION SUBSURFACE EXCAVATION
在线阅读 下载PDF
导出
摘要 北京地铁首都机场线二期(西延)工程全线采用非降水暗挖法施工,其中北新桥站采用PBA暗挖法施工,小导洞采用注浆止水,经多种方案比选决定,该车站四周围护结构首次采取洞内咬合桩止水。施工实践证明,咬合桩咬合严密,止水效果良好。 Beijing capital airport subway line phase II(west extension)adopted non-dewatering subsurface excavation method along the whole line.PBA subsurface excavation method was adopted in construction of Beixinqiao station and grouting water-stop method was used for small guide hole.After comparison among different construction methods,it was determined to adopt in-hole secant pile water-stop method for the first time for the enclosure structure of the station.The construction practice showed that the secant pile is tight and favorable water-stop effect was realized.
作者 张东 李春茂 孙青龙 王伟 ZHANG Dong;LI Chun-mao;SUN Qing-long;WANG Wei(Beijing Construction Engineering Group Co.,Ltd.,100055,Beijing,China)
出处 《建筑技术》 2020年第7期782-785,共4页 Architecture Technology
关键词 地铁暗挖车站 不降水施工 咬合桩 subsurface excavation subway station non-dewatering construction secant pile
  • 相关文献

同被引文献26

引证文献4

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部