摘要
文章结合燃煤电厂机组管理问题,对发电机组集控管理和协调控制系统优化设计思路进行探讨,提出采用阶梯式系统框架结构实现一对多控制,确保机组能够实现电网负荷变化快速响应,从而满足负荷调节要求。
Based on the problems of unit management in coal-fired power plants,this paper discusses the optimal design ideas of the centralized control management and coordinated control system of generating sets,and puts forward the use of stepped system frame structure to realize one-to-many control,so as to ensure that the unit can achieve rapid response to changes in power grid load to meet the load regulation requirements.
作者
李骁
LI Xiao(Shanxi Zhangze Electric Power Changzhi Power Generation Co.,Ltd.,Changzhi 046000,China)
出处
《电工技术》
2020年第10期60-61,63,共3页
Electric Engineering
关键词
燃煤电厂
集控运行
机组协调控制
coal-fired power plant
centralized control operation
unit coordinated control