双曲线冷却塔内超高脚手架上人通道施工技术 被引量:1

Construction Technology of Human Passage on Super-high Scaffolding in Hyperbolic Cooling Tower
在线阅读 下载PDF
导出
摘要 在2000 m2双曲线形冷却塔工程施工过程中,为保证施工人员能从作业面安全上下,采用了超高钢管脚手架上人通道。超高钢管脚手架上人通道安全风险大,稳定性较差。介绍了超高脚手架平面布置、连墙装置、缆风绳设置、脚手架搭设拆除要点,实践证明是可行的。 In the construction process of the 2000 m2 hyperbolic cooling tower project,in order to ensure that the construction workers can safely get up and down from the working surface,the super-high steel scaffolding pedestrian passage is adopted.The superhigh steel pipe scaffolding has a large safety risk and poor stability.This paper introduces the super-high scaffolding plane layout,wallconnecting device,cable wind rope setting,scaffolding detachment points,which proved to be feasible.
作者 朱惠伟 Zhu Hui-wei
出处 《建筑技术开发》 2020年第4期77-78,共2页 Building Technology Development
关键词 双曲线冷却塔 超高脚手架 上人通道 连墙装置 缆风绳 hyperbolic cooling tower super-high scaffold upper passage wall installation cable rope
  • 相关文献

同被引文献15

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部