摘要
简要介绍了苏阿皮蒂水电站金属结构设备的整体布置、设计选型和运行方式,并着重对电站快速门液压机布置方式、3号导流洞封堵门启闭机与泄洪底孔事故门启闭机永临结合方法和泄洪底孔工作门模型试验研究及优化进行了阐述。
The overall layout,design selection and operation mode of the metal structure equipments in Souapiti Hydropower Station are briefly introduced.The layout of the hydraulic hoist of stop gate,the combination way for the permanent and temporary operation of the hoist of No.3 diversion tunnel blocking gate and the hoist of emergency gate of flood discharging bottom outlet,and the model test and optimization of the service gate for the flood discharging bottom outlet are emphatically expounded.
作者
周伟
侯庆宏
丁正忠
谢腾飞
ZHOU Wei;HOU Qinghong;DING Zhengzhong;XIE Tengfei(Yellow River Engineering Consulting Co.,Ltd.,Zhengzhou 450003,Henan,China)
出处
《水力发电》
北大核心
2020年第1期61-63,88,共4页
Water Power