甲方供应在几内亚苏阿皮蒂项目中的积极作用 被引量:1

The Positive Effect of Party A s Material Supply in the Construction of Souapiti Hydro Project in Guinea
在线阅读 下载PDF
导出
摘要 围绕“高风险”的市场条件和“甲方掌控”的必要性展开,分析了在几内亚特殊市场条件下,甲方控制对保障项目物资供应和施工进度、以及成本控制的积极作用。苏阿皮蒂水电站于2016年开工建设,是几内亚迄今为止开发的最大水力发电项目,工程量大、工期紧,如何保证主材物资供应是难点之一。经实践证明,甲方在物资供应中的深度参与能够对项目顺利开展发挥积极作用,保证了主材物资供应和施工的顺利开展,同时也降低了项目建设成本。 Based on the market conditions of“High risk”and the necessity of“Controlling by Party A”,the positive effects of Party A s control on material supply,construction progress and cost control under the special market conditions in Guinea are analyzed.The construction of Souapiti Hydropower Station starts in 2016 and it is the largest hydropower project developed by Guinea so far.With a large amount of construction quantity and tight schedule,the supply of main materials is always one of the principle difficulties.It has been proved by practice that Party A s deep participation in material supply can play an active role in the successful implementation of project,which ensures the smooth development of material supply and project construction,and also reduces construction cost.
作者 逄亮 胡洋 寿开 白杨 PANG Liang;HU Yang;SHOU Kai;BAI Yang(China International Water&Electric Corp.,Beijing 100120,China)
出处 《水力发电》 北大核心 2020年第1期14-16,60,共4页 Water Power
关键词 设备物资供应风险 甲方供应 苏阿皮蒂水利枢纽 几内亚 risk of material supply supply of Party A Souapiti Hydro Project Guinea
  • 相关文献

参考文献8

二级参考文献22

共引文献51

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部