海口中心大型多隔板钢管混凝土柱施工技术研究 被引量:2

Construction of Large-scale Concrete Filled Steel Tube Column with Multi-clapboard
在线阅读 下载PDF
导出
摘要 海口中心为288m高纯钢结构建筑,主楼结构柱均为钢管混凝土柱,钢管柱截面规格多达40余种。钢管混凝土采用高抛法浇筑,最大倾落高度达12.6m,钢管柱内部有多道横隔板及纵隔板,对施工技术要求高。为确保钢管内混凝土的密实度和强度,分别进行钢管柱截面设计、混凝土配合比优化、浇筑模拟试验、施工工艺改进及密实度检测等多方面研究,总结出一套适用于本工程的施工技术。利用该技术指导现场施工,保证了施工质量。 Haikou Center Project is 288 meters high with a full-steel structure. All of the structural columns of the main building are concrete filled steel tube. There are over 40 kinds of section specifications of the columns. The concrete is pouring by high pouring method and the pouring height is up to 12. 6 m. There are many clapboards inside,causing the high requirement for construction. To ensure the compactness and strength of the concrete in the tube,a series of techniques including section design,mix proportion design, simulation test, improvement of construction method,compactness detection are researched and a set of construction techniques for this project is summarized. The construction quality is guaranteed by using the techniques.
作者 谢孝成 郭杜魁 郝文彬 周华 赵汝强 XlE Xiaocheng;GUO Dukui;HAO Wenbin;ZHOU Hua;ZHAO Ruqiang(Beijing Fourth Construction & Engineering Co. , Ltd. , Beijing 100075, China)
出处 《施工技术》 CAS 2018年第3期1-3,35,共4页 Construction Technology
关键词 高层建筑 钢管混凝土 高抛法 密实度 施工技术 tall buildings concrete filled steel tube high pouring method compactness construction
  • 相关文献

参考文献6

二级参考文献33

共引文献36

同被引文献15

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部