针对江西洪屏抽水蓄能电站300 MW机组励磁系统控制功能和各主要组成装置的设计原则,江西洪屏抽水蓄能电站励磁系统机电设备通过安装、调试、试验,各性能指标均达到并优于国家标准,符合设备合同要求和相关技术条款的规定,满足了运行要求。洪屏抽水蓄能电站首台机组投入运行,实现了江西电网抽水蓄能零的突破,在区域电网中开始发挥"稳压器""蓄电池""调节器"的作用。
The design and application of the excitation system for the 300 MW generator units in Jiangxi Hongping Pumped Storage Power Station are presented. Specifically, the design principles of the control functions and main components are introduced. After the installation, commissioning and testing, the performance parameters of the electro-mechanical devices in the excitation system are all superior to the national standard, contract requirements and relevant technical provisions. Thus, the operation requirements of the system are satisfied. The success operation of the first unit in Hongping Pumped The power station Storage Power Station is a memorable breakthrough of pumped storage in the Jiangxi power grid. begins to play its role of the stabilizer, battery and regulator in the regional power grid.
出处
《水电与新能源》
2018年第1期61-67,共7页
Hydropower and New Energy
关键词
抽水蓄能
励磁系统
设计原则
pumped storage
excitation system
design principle