摘要 针对梯级水电站群中期调度水流滞时问题,引入滞时电量概念,建立了梯级水电站群中期调度期末蓄能最大模型;采用基于两阶段次梯度法乘子更新策略的拉格朗日松弛方法进行模型求解,第一阶段通过系数递增策略快速确定乘子初始值,第二阶段采用递减策略加快算法收敛速度。以澜沧江中下游梯级6座水电站群中期优化调度为实例进行仿真,结果表明,所提出的求解方法能提供较好的求解质量;考虑滞时电量能提高水电系统的期末蓄能,中期调度需充分考虑调度结果的后效性。 In view of the problem of inflow delay in medium-term operation of cascade hydropower stations, a concept of delayed energy is introduced, and a stored energy maximization model was constructed for the end of the operation period. A Lagrange relaxation method based on a two-stage subgradient algorithm used to update multipliers is proposed to solve the model. In the first stage, the initial multipliers are rapidly determined by increasing coefficients gradually. In the second stage, the convergence speed is increased by decreasing coefficients gradually. The proposed model and solution method were applied to medium-term optimal operation of six hydropower stations located in the middle and lower reaches of the Lancang River. The results show that the proposed method can obtain good solutions, considering delayed energy can increase stored energy of the hydropower system for the end of the operation period, and the post-effect of medium-term operation should be considered sufficiently.
出处 《水利水电科技进展》 CSCD 北大核心 2016年第4期59-64,共6页 Advances in Science and Technology of Water Resources
基金 国家自然科学基金(51209031 51109024)
关键词 梯级水电站群 优化调度 中期调度 蓄能最大模型 滞时电量 拉格朗日松弛方法 cascade hydropower stations optimal operation medium-term operation stored energy maximization delayed energy Lagrange relaxation method
  • 相关文献

参考文献18

  • 1张雯怡,黄强,畅建霞.水库发电优化调度模型的对比研究[J].西北水力发电,2005,21(3):47-49. 被引量:5
  • 2梅亚东,杨娜,翟丽妮.雅砻江下游梯级水库生态友好型优化调度[J].水科学进展,2009,20(5):721-725. 被引量:39
  • 3YOO J H. Maximization of hydropower generation through the application of a linear programming model [ J ]. Journal of Hydrology,2009,376(1/2) : 182-187.
  • 4HINCAL O, ALTAN-SAKARYA A, METINGER A. Optimization of multireservoir systems by genetic algorithm [ J ]. Water Resources Management, 2011,25 ( 5 ) : 1465- 1487.
  • 5WANG J W, YUAN X H, ZHANG Y C. Short-term scheduling of large-scale hydropower systems for energy maximization [ J ]. Journal of Water Resources Planning and Management ,2004,130 ( 3 ) : 198-205.
  • 6BRAGA B P F,YEH W W G, BECKER L,et al. Stochastic optimization of muhiple-reservoir-system operation [ J ]. Journal of Water Resources Planning and Management, 1991,117(4) :471-481.
  • 7. YU Z W,SPARROW F T, BOWEN B H. A new long-term hydro production scheduling method for maximizing the profit of hydroelectric systems [ J ]. IEEE Transactions on Power Systems, 1998,13 ( 1 ) :66-71.
  • 8陈森林,万俊,刘子龙,乐玉华.水电系统短期优化调度的一般性准则(1)——基本概念与数学模型[J].武汉水利电力大学学报,1999,32(3):34-37. 被引量:14
  • 9张双虎,黄强,蒋云钟,殷峻暹.梯级电站长期负荷分配模型及其求解方法[J].西安理工大学学报,2009,25(2):135-140. 被引量:4
  • 10BARROS M T L, TSAI F T C, YANG S L, et al. Optimization of large-scale hydropower system operations [ J ]. Journal of Water Resources Planning and Management,2003,129 ( 3 ) : 178-188.

二级参考文献51