摘要
介绍了大山清水泵站由于供电线路632#、625#实现双回路电源改造,两条线路互为备用,所以这个改造的同时有必要对泵站内的配电设施进行优化,调整部分变压器负荷,增加负荷大的变压器,同时其对应的开关设备等一并更换,解决一些不必要的安全问题,从而使泵站达到最佳经济运行状态,真正保证泵站安全稳定高效供水。
Due to the transformation of power supply circuit 632# and 625#, two circuits are the backup line for each other, it is necessary to optimize pump station distribution facilities at the same time. We adjust some transformers' load, increase transformers with high load, and change the switch equipment together, not necessary to solve some security problems, so that the pumping station can achieve the best economic operation and supply water safely, stably and efficiently.
出处
《铜业工程》
CAS
2016年第4期98-100,共3页
Copper Engineering
关键词
清水泵站
生产工艺
优化
主变
经济运行
负荷
water pumping station
production process
optimization
main transformer
economic operation
load