烧房沟滑坡型泥石流工程治理及效果分析 被引量:8

ENGINEERING MEASURES AND THEIR EFFECT FOR MOBILIZATION OF DEBRIS FLOW FROM LANDSLIDES AT SHAOFANGGOU STREAM VALLEY
在线阅读 下载PDF
导出
摘要 国内对泥石流治理措施谷坊坝、格栅坝的作用和效果研究较多,而对滑坡型泥石流的综合治理措施和效果研究较少。2010.8.14强降雨过程导致汶川震区映秀镇烧房沟滑坡型泥石流暴发,通过分析其运动过程和现状沟道特征,结合滑坡堵点和沟道深切的特点,治理工程采用"防堵防切"综合工程结构形式:"上游谷防群+中游抗滑桩、挡土板和肋板护脚护底+下游3座格栅坝+渡槽明洞跨越G213",并分析各分项工程作用:"减弱龙头动能"+控制LS01堵点、保护"鞋尖"+"拦粗放细"、"顺畅排导"。最后利用"2010.8.14"与"2013.7.10"的历史降雨量和固体参与量对比、工程治理前后动储量对比和各分项工程治理前后的沟道特点对比,验证了烧房沟滑坡型泥石流综合治理工程的效果良好。为今后震区滑坡型泥石流工程防治提供参考。 The function and effect of check dams and griile dams in certain catchments are studied extensively in China.However,there has been comparatively little research oncontrol measures and their effect to mobilization of debris-flow from landslides.A rainstorm induced debris flow hazard occurred on August 1 4,2008 in Yingxiu Town of Sichuan Province,where was affected by the Wenchuan earthquake.The paper examines the motion process and the gully characteristics,landslides blocking point,the high depth of cutting,and their combinations.It is discovered that the whole basin comprehensive treatment shall prevent clogging and cutting.In order to control debris flow disaster happening again,check dams can weaken the leading kinetic energy in the upper reaches of the valley.Retaining plate and bed boards can control the landslide blocking point and protect the toecap in the middle reaches of the valley.Grillage damsand aqueduct can intercept the coarse particle and discharge debris flow smoothly.Then the paper compares the accumulated rainfall,solid matter involved in quantity,dynamic energy reserves and the gully characteristics around control measures.After discussing the initiation,the engineering measures for mobilization of debris-flow from landslides at Shaofang stream course has a good result.It provides a reference for engineering measures for debris-flow mobilization from landslides in the earthquake areas.
出处 《工程地质学报》 CSCD 北大核心 2016年第2期220-227,共8页 Journal of Engineering Geology
基金 科技基础性工作专项工作(2011FY110103) 国家科技支撑计划项目(2011BAK12B01)资助
关键词 滑坡型泥石流 堰塞体 工程治理 效果分析 汶川地震 烧房沟 Debris-flow mobilizationfrom landslides Damming object Engineering measures Effecte valuation Wenchuan earthquake Shaofang gully
  • 相关文献

参考文献14

二级参考文献132

共引文献589

同被引文献104

引证文献8

二级引证文献48

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部