根据新建铁路南京枢纽京沪高速大胜关长江大桥南引桥的实践,提出了MZ900S型上承式移动模架在高墩、地基条件差以及频繁转场项目条件下的拼装方案,并就该项技术方案的效率及经济性进行了分析。
According to the practice of the new railway hub of Nanjing Dashengguan Yangtze River bridge of Beijing Shanghai high speed south approach,the paper proposed assembly scheme of MZ900 S deckmovable scaffolding system in high pier,foundation condition is poor and the frequent transitionproject condition,and the efficiency on the technique scheme is analyzed.