摘要
本文通过实例利用 AOE 网用以模拟工程的事件和任务.采用顶点标号法,在标号过程中运用横向搜索法,计算出完成工程的最短时间,非关键事件和任务的缓冲时间等,并给出了程序框图.
In this paper,through an example,we apply AOE-net work to simulate the events and tasks in a project,The shortest time limits for computing the projeet and the buffer time limits for the unimportant events and tasks etc.have been calculated by using a top-mark algorithm and crosswise search in the marking process.Meanwhlie the flowchart of this algorithm is shown as well.
出处
《河北工学院学报》
1989年第2期97-105,共9页
Journal of Hubei Polytechnic University