摘要
介绍了运用试验设备、继保录波和状态判断等多种手段分析处理 110kV母线短路电流冲击造成一台 2 2 0kV主变内部故障的经验。
As main equipment in power system, it is urgent and difficult to analysis fault reason and repair quickly when fault is discovered in transformer. From the fact that a 220 kV transformer was damaged by short-circuit of 110 kV busbar, it primarily describes fault reason from electric experiments, relay action and fault record, and also gives repair project.