摘要
针对凹山采场西北帮边坡的实际情况 ,在稳定性分析计算的基础上 ,进行了削坡、护坡、加固、排水等一系列综合治理设计 ,并在分项逐步实施 。
In view of the real situation of the northwest wall slope in Aoshan Pit and on the basis of the calculation of stalility anslysis,a systematic design of comprehensive control including slope cutting,protection,consolidation and drainage was made and implemented in steps.The expected aim of control was achieved.
出处
《金属矿山》
CAS
北大核心
2001年第7期14-15,35,共3页
Metal Mine