摘要
以精度高、速度快的二、三维非线性迭代先进节块法扩散计算程序 NLNEM和节块精细功率重构程序 3DPPREC为基础,参照 SIMULATE的功能研制了具有多种热工反馈功能的三维压水堆燃料管理程序 CSIM- 3。用该程序对秦山核电厂第 1、 2循环进行跟踪计算。结果表明,功率及燃耗分布相对误差小于 5%,除个别测量点上临界硼浓度计算值与测量值的误差超过 50μ g· g- 1外,其余均小于 50μ g· g- 1,而控制棒价值、硼浓度微分价值、温度系数误差也均在工程要求的范围之内。
Based on the advanced 2-D and 3-D nonlinear iteration nodal code with high accuracy and efficiency NLNEM and intro-nodal pin power reconstruction code 3DPPREC, a multi-functional, physics-hydraulic coupled code of PWR fuel management calculation CSIM-3 is encoded. The load following calculation for cycle 1 and 2 of Qinshan Nuclear Power Plant has been performed. Compared with the measured data, the results show that the maximum errors of relative power density and burn-up are -1. The maximum errors of control rod value, differential values of boron concentration and moderator temperature coefficient are all within the permissible limits of engineering requirement.
出处
《核动力工程》
EI
CAS
CSCD
北大核心
2001年第4期370-375,379,共7页
Nuclear Power Engineering
基金
国家自然科学基金资助项目(19875039)