摘要
本文针对以礼河电站存在的问题,对水斗式水轮机的振动问题进行了详细分析计算。利用A475a_170转轮替代P2_170转轮,振动减轻,出力增加,效率提高,增容减振效果明显。
In this paper vibration problem of Pelton turbine is analyzed and calculated for Yilihe power station.The results of decreasing vibration ,increasing output and the raising efficiency of the turbine were obtained replaced P2_170 runner byA475a_170 runner.
出处
《大电机技术》
北大核心
2001年第2期48-51,共4页
Large Electric Machine and Hydraulic Turbine