大跨三桁铁路斜拉桥桁间高差控制技术 被引量:3

Truss Elevation Difference Control Technique for Long-Span Three-Truss Railway Cable-Stayed Bridge
在线阅读 下载PDF
导出
摘要 钢桁梁斜拉桥钢桁梁采用3片主桁结构,在自重作用下中桁承担荷载较大,施工中容易出现桁间高差(中桁比边桁低),造成钢桁梁连接杆件拼装困难。以宁安铁路安庆长江大桥为背景,通过加强测量观测,控制连接杆件螺栓施拧、桥面板焊接工艺及进度,调整主桁杆件架设顺序等具体措施,有效保证了钢桁梁的架设进度及合龙精度。 The steel truss girder cable-stayed bridge usually adopts the three-truss main girder structure .Under the action of self-weight ,the middle truss bears heavier loads ,which will lead to elevation difference among trusses during the construction process (the middle truss is lower than the side trusses) ,and consequently ,the assembly of the connecting chords of the steel truss girder will be difficult .The Anqing Changjiang River Bridge on the Ningbo-Anqing Railway was taken as the background in this study .A series of specific measures were taken ,such as intensifying efforts to do observation and measurements ,controlling the tightening of the bolts in the connecting chords and the welding workmanship and progress of the deck plate and adjusting the erection sub -sequence of the main truss chords ,so as to effectively ensure the erection schedule and closure ac-curacy of the steel truss girder .
作者 洪清庄
出处 《世界桥梁》 北大核心 2014年第2期22-25,共4页 World Bridges
关键词 斜拉桥 钢桁梁 架设 散拼法 高差 施工控制 cable-stayed bridge steel truss girder erection piece-by-piece assembly eleva-tion difference construction control
  • 相关文献

参考文献10

二级参考文献30

共引文献107

同被引文献21

引证文献3

二级引证文献31

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部