大型通廊钢结构吊装措施及实例分析 被引量:3

HOISTING MEASURE AND INSTANCE ANALYSIS OF LARGE STEEL STRUCTURE CORRIDOR
在线阅读 下载PDF
导出
摘要 介绍了大型通廊钢结构型式、吊装顺序、吊装机具选择及主要吊装措施。通过对德钢1 350m3高炉Z-1上料皮带机通廊吊装进行分析,详细阐述复杂地形条件下,选择不同规格吊装机械对通廊进行分片、分段、整体吊装的施工方法,通过采取措施严格控制通廊支架、桁架从拼装到吊装的每一个环节,确保通廊钢结构安装全过程的安全性。 It was introduced the structure type of large corridor,hoisting order,choice of hoisting appliance and major hoisting measures.By analyzing the hoisting of Z-1 feeding belt conveyer of Degang 1 350 m3 blast furnace,it was elaborated the measures for every link from assembling to hoisting,when carrying out segment erection and overall lifting structure of the corridor,and hoisting machine with different size was chosen.The bracket and truss were controlled strictly under complicated terrain,to ensure the safety of erection.
作者 周志国
出处 《钢结构》 2014年第2期71-75,共5页 Steel Construction
关键词 通廊结构 吊装机械 吊装措施 工程应用 corridor structure hoisting equipment hoisting measure project practice
  • 相关文献

参考文献7

  • 1GB50372-2006炼铁机械设备工程安装验收规范[S].
  • 2GB50683-2011.现场设备、工业管道焊接工程施工质量验收规范[s].
  • 3GB50755-2012,钢结构工程施工规范[S].
  • 4GB50661-2011钢结构焊接规范[S].
  • 5GB50205-2001.钢结构工程施工质量验收规范[S].[S].,..
  • 6GB50252-2010,工业安装工程施工质量验收统一标准[S].
  • 7周志国.高炉粗煤气系统球节点安装方法[J].钢结构,2013,28(10):74-77. 被引量:2

二级参考文献6

  • 1GB50372-2006炼铁机械设备工程安装验收规范[S].
  • 2GB50661-2011钢结构焊接规范[S].
  • 3GB50205-2001.钢结构工程施工质量验收规范[S].[S].,..
  • 4GB50252-2010,工业安装工程施工质量验收统一标准[S].
  • 5GB506832011现场设备、工业管道焊接工程施工质量验收规范[S].
  • 6GB507552012钢结构工程施工规范[S].

共引文献805

同被引文献18

引证文献3

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部