副立井井筒冻结设计方案及施工技术 被引量:7

Freezing Shaft Design Plan and Construction Technology of Mine Auxiliary Shaft
在线阅读 下载PDF
导出
摘要 为了保证井筒能顺利通过松散巨厚表土层,在井筒施工过程中采取"主排孔+辅排(外)孔+辅排(内)孔"冻结方案,介绍了冻结法施工的优点,确定了井筒的冻结深度及冻结壁厚度,对冻结孔、水文孔及测温孔布置参数进行了设计,并对冻结法施工工艺进行了详细论述,可为类似地质条件冻结施工技术提供了有力的技术支撑和科学保障。 In the process of shaft construction, in order to ensure the smooth cross of auxiliary shaft through ultra - thick loose alluvium, the freezing scheme of "main exhaust hole + auxiliary row (outer) hole + auxiliary row (inner) hole" was applied. The paper introduced the advantages of freezing method construction, the freezing depth and frozen wall thickness of the shaft were determined, and the arrangement parameters of freezing hole, hydrological hole and thermometer hole were designed, and the process of freezing method construction was discussed in detail.
作者 薛毅宏
出处 《煤炭工程》 北大核心 2014年第3期29-31,共3页 Coal Engineering
关键词 冻结法 表土层 冻结孔施工 差异冻结方式 钻孔质量控制 freezing method alluvium freezing hole construction diversity - freezing method quality control ofborehole
  • 相关文献

参考文献10

二级参考文献31

共引文献407

同被引文献42

引证文献7

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部