独立桩脚自升式钻井平台在我国海洋石油勘探开发中的应用已有三十多年的历史,在长期平台插桩分析工作的基础,虽然积累了丰富的经验,但面对新的勘探区域,也会出现预测不准的情况。究其原因主要是对场地土质条件了解不够充分、土质参数评价不够准确、计算模型过于单一和地区经验积累不足等。为提高插桩分析结果的准确性,通过多次工程插桩实践,总结了插桩分析几个需重点关注问题。结合某工程实例,在考虑这些关键问题的基础上,得到插桩分析预测结果与实际插桩结果基本吻合。
The Jack-up rig has been utilized in the development of offshore oil for more than thirty years in China. A lot of Jack-up rig leg penetration analysis has been carried out and rich experiences have been accumulated. However, the predicted leg penetration results were inconsistent with those actual leg penetration results in some new oilfield development area. The main reasons lay in the insufficient understanding of soil properties, unsuitable soil parameters, simplicity of calculation model and the lackness of local experiences etc. To improve the accuracy of predicted penetration, the important considerations for jack-up rig leg penetration analysis were summarized through many engineering practices in this paper. The predicted results coincided with the actual results based on those considerations in an actual case.
出处
《海洋通报》
CAS
CSCD
北大核心
2014年第1期84-89,共6页
Marine Science Bulletin