厦门会展中心二期展厅跨度81米,施工工期异常紧张,采用张弦梁体系取得技术安全、质量可靠、工期短、造价经济、结构美观的良好效果,通过对会展中心张弦梁体系的选型、设计、施工难点分析,介绍了张弦梁结构的受力性能及应用实践,可供类似工程参考借鉴。
The roof structure system of the Conference and Exhibition Center is a beam string structure, its pre - stressing is very difficult. A minute description of the pre - stressing construction plan is given. Some first - phase preparations such as the construction simulation calculation and pre - stressing device design are introduced. The construction monitor plan and the synchronism control measure are briefly accounted. According to the construction simulation results and site construction monitoring result, the feature of pre - stress and steel structure construction of the structure are proposed.
出处
《福建建设科技》
2014年第1期28-30,共3页
Fujian Construction Science & Technology
关键词
张弦梁
选型
设计施工
Beam String Structure
design
construction