基于逆流水步距组织分层无节奏流水施工 被引量:2

Opposite Pipelining Space for Multiple Layers Construction Management on Non-equal Flow Process
在线阅读 下载PDF
导出
摘要 基于不分层时流水工期的定义公式,考虑了组织无节奏流水施工的关键约束条件,通过引入逆流水步距参数,推导出分层时无节奏流水的参数化工期模型,并以某5栋两层的别墅群为例编制了进度计划横道图.结果表明:该参数化工期模型可有效应用于分层时的无节奏流水,且与流水工期定义公式的参数结构吻合一致;在施工段数大于施工过程数的前提下,该模型有效表达了主导施工过程连续作业的关键约束性质;在层间工程量相同的前提下,该模型较好地体现出流水施工的节奏性、均衡性及专业性等特点. Based on the definition equations of flowing water construction with the response of key constraints, the duration model of non-rhythm flow process is established with working out construction progress plan by adopting network transverse lined diagram. It is found that the model can be well used for the non-rhythm flow process and coincide with the parameter structure of the definition equations of flowing water construction. The key constraints of non-rhythm flow process can be well respond by the model. And the flow construction characteristics such as rhythm, balance, professional are better reflected.
出处 《合肥学院学报(自然科学版)》 2014年第1期92-96,共5页 Journal of Hefei University :Natural Sciences
基金 安徽省教育厅基金项目(2012jyxm584) 安徽新华学院基金项目(2011jy003 2012jgkcx01) 安徽新华学院骨干教师资助项目(2012xgg03)资助
关键词 无节奏流水 施工层 流水工期 参数化模型 逆流水步距 non-rhythmic flow precess construction layer flow duration parametric model opposite pipelining space
  • 相关文献

参考文献6

二级参考文献3

共引文献19

同被引文献18

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部