摘要
本文分析了低负荷运行方式电厂调峰机组间负荷优化分配原理,给出了负荷优化分配通用计算程序.对负荷经济调度出现的问题作了讨论,并以诧城电厂为例,进行了具体计算,给出了低负荷运行调峰时其负荷优化分配曲线.
This paper describes the fundamentals of optimizing load distribution among variable-load units in a part-load operating plant. The common computation code was presented for optimizing load distribution, and some problems in economical load distribution were discussed. Using the computation code, calculations were made for the units in Chacheng Power Plant, and the optimized load-distribution curve during part-load operation was obtained.