以兰新第二双线红柳河特大桥施工为例,简要介绍了总体施工方案,着重对"筑土台"法填筑及其检算进行了论述,指出该方法在确保工期、保证安全、降低成本等方面均取得了良好的效果。
Taking Hongliu river bridge of Lanxin second double-line construction as an example, the paper briefly introduced the general con- struction scheme, emphatically discussed the "Building Stereobate" method filling and its checking, pointed out that this method achieved good results in ensuring construction period, ensuring safety, reducing cost and other aspects.
出处
《山西建筑》
2013年第26期152-154,共3页
Shanxi Architecture
关键词
箱梁
承载力
检算
支撑块
box beam, bearing capacity, checking, supporting block