上海轨道交通12号线11标工程地处徐汇区滨江开发区,工程主要包括2个区间隧道工程,采用4台Φ6340盾构推进。随着建筑业科技水平的迅猛提高,为了进一步加强对施工过程中产品质量、安全风险和物资设备的动态监控,建立一套完整的数字化工地管理系统已经成为未来的主流趋势,上海城建市政工程(集团)有限公司数字化工地建设就是通过物联网技术结合轨道交通施工而建设的数字化施工管理系统。
The 11^th bid segment of No.12 of Shanghai railway is located at Binjiang developed area, Xuhui distract. The project is had two blocks of tunnel, and adopt 4 shield machines Φ6340 to excavating. For improve the dynamic supervision and control of product quality, safety risk, material and equipment during construction, built a set of digitalized site management system have been the future direction. The digitalization site built up of Shanghai urban construction municipal engineering (group) Co., Ltd., is a digitalized site management system by networking technology combine with railway construction.
出处
《工程质量》
2013年第7期67-72,共6页
Construction Quality
关键词
轨道交通
数字化
工地建设
railway traffic
digitalization
construction site