带有约束的轨道门吊优化调度问题研究 被引量:2

Research on Rail-mounted Gantry Crane Scheduling with Constraints
在线阅读 下载PDF
导出
摘要 为提高铁路集装箱中心站的运作效率,研究了带有干涉约束和安全约束的轨道式门式起重机的调度问题,以最小化最大装卸作业时间为目标构建了一个混合整数规划模型。由于该模型求解难度大,为此提出了一种萤火虫优化算法(FA),使用小规模和大规模随机算例对算法进行测试。测试结果表明:无论是求解小规模问题还是大规模问题,FA算法都比CPLEX和GA算法具有较快的寻优速度和较高的寻优精度。 To improve the operation efficiency of railway container terminals,the rail-mounted gantry cranes scheduling problem(RMGCSP) is studied with consideration of interference and safety distance between these cranes.In order to minimize makespan of the train loading/ discharging operation,a mixed integer programming model for the considered RMGCSP is formulated.In the view of the solving difficulty,a firefly algorithm(FA) is proposed.The effectiveness of the FA is evaluated on some random instances both small scale and large scale.Experimental results show that the FA algorithm can search for global optimization more quickly and precisely than CPLEX and GA.
出处 《西华大学学报(自然科学版)》 CAS 2013年第4期77-82,共6页 Journal of Xihua University:Natural Science Edition
基金 四川省教育厅项目(12ZB322) 西华大学制造与自动化省高校重点实验室开放研究基金资助项目(szjj2012-023)
关键词 铁路集装箱中心站 轨道吊调度 干涉约束 安全约束 萤火虫优化 railway container terminal gantry crane scheduling interference constraint safety constraint glowworm swarm optimization
  • 相关文献

参考文献19

  • 1Daganzo, C F. The Crane Scheduling Problem. [ J ]. Transporta- tion Research Part B: Methodological,1989,23 (3) : 159 -175.
  • 2Lim A, Rodrigues B, Xiao F, et al. Crane Scheduling with Spa- tial Constraints [ J ]. Naval Research Logistics,2004,51 ( 3 ) : 386 - 406.
  • 3Moccia L, Cordeau J - F, Gaudioso M, et al. A Branch and Cut Algorithm for the Quay Crane Scheduling Problem in a Container Terminal [ J ]. Naval Research Logistics,2006,53 ( 1 ) : 45 - 59.
  • 4Ng W C, Mak K L. Quay Crane Scheduling in Container Termi- nals[J]. Engineering Optimization,2006,38 (6) : 723 -737.
  • 5Bierwirth C, Meisel F. A Fast Heuristic for Quay Crane Schedu- ling with Interference Constraints [ J ]. Journal of Scheduling, 2009, 12 (4) : 345 -360.
  • 6Legato P, Trunfio R, Meisel F. Modeling and Solving Rich Quay Crane Scheduling Problems [ J ]. Computers & Operations Research, 2012,39 (9) :2063 -2078.
  • 7Zhu Y, Lim A. Crane Scheduling with Non - crossing Constraint [ J ]. Journal of the Operational Research Society, 2006, 57: 1464 - 1471.
  • 8Sammarra M, Cordeau J F, Laporte G, et al. A Tabu Search Heuristic for the Quay Crane Scheduling Problem[ J]. Journal of Schedu- ling,2007,10 (4-5) : 327 -336.
  • 9Lee D -H,Wang H Q,Miao L. Quay Crane Scheduling with Non -interference Constraints in Port Container Terminals[ J]. Transpor- tation Research Part E: Logistics and Transportation Review, 2008,44 (1): 124-135.
  • 10史峰,黎新华,秦进,邓连波.单线列车运行图铺划的时间循环迭代优化方法[J].铁道学报,2005,27(1):1-5. 被引量:26

二级参考文献52

共引文献110

同被引文献9

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部