摘要
在土方开挖工程中 ,汽车要等待挖土机挖土 ,汽车就是顾客 ,挖土机就是服务机构 ,二者形成一个排队系统。结合天津市紫金花园工程“逆筑法”土方工程施工组织 ,运用排队理论解决土方挖运的施工组织问题 ,并得出在一定施工组织下土方开挖的效率和成本曲线 ,保证日出土量与机械配置在经济上达到最优。
In an earthwork,the conveyance is like a consumer due to waiting for necessary loading capacity,and then an excavator is the same as a service system.With queuing theory,the problem of the organization of the earthwork construction is solved in the Violet Gold Garden project with reverse construction method and the curves on efficiency and cost are given to make the machine disposition optimized economically.