摘要
针对新疆哈密地区戈壁地带干燥少雨、昼夜温差大、冬季严寒的地域实况,结合大南湖电厂供热工程实践,介绍了供热管道无补偿直埋敷设工艺原理,探讨了管道安装施工工艺流程及操作要点,从而确保供热工程顺利按期投产及安全稳定运行。
For the the Xinjiang Hami area Gobi Strip drying drier large temperature difference between day and night, winter cold geographical live, combined Dananhu power plant heating engineering practice, heating pipe compensation for direct burial process principles, discussed the pipeline installation and construction processprocesses and operating points, ensuring smooth schedule put into operation and the safe and stable operation of the heating project.
出处
《工程建设与设计》
2013年第5期158-160,共3页
Construction & Design for Engineering
关键词
供热管道
直埋无补偿管道施工
质量控制
方案
heating ducts
direct burial without compensation pipeline construction
quality control
program