摘要
受施工条件限制,羚山排涝泵站施工原设计的导流方案不能使用,结合施工现场实际条件,采用预制混凝土涵管导流方案进行施工,取得很好的效果。
Subject to the conditions of the construction, the original design of the pump station construction diversion scheme can not be used. However, in accord with the actual conditions of the construction site, construction of precast concrete culvert pipe diversion program has achieved favorable results.
出处
《广东水利电力职业技术学院学报》
2013年第1期55-58,共4页
Journal of Guangdong Polytechnic of Water Resources and Electric Engineering
关键词
预制涵管
导流
设计
施工
precast culvert pipe
diversion
design
construction