摘要
山区小型河流引水式水电站开发时,需考虑到下泄生态流量的问题。以四川省九龙县二台子水电站为实例,采用Tennant法和R2-CROSS法计算其生态流量并对比分析,针对二台子水电站坝首已完工的特点,进一步探讨其下泄生态流量的工程措施与可行性。
The discharge of the ecological flow should be considered when the diversion type hydropower stations are developed in small rivers of mountain area. Taking Ertaizi hydropower station as example, the paper Calculates ecological flow in the ways of Tennant and R2 - CROSS, and takes a further research about the engineering measures of discharging ecological flow.
出处
《水利科技与经济》
2013年第4期78-80,共3页
Water Conservancy Science and Technology and Economy
关键词
水电站
下泄生态流量
工程措施
hydropower station
ecological flow