在青海大通河纳子峡水电站混凝土面板堆石坝砂砾石料填筑碾压试验中,对其场址、用料和仿真施工布置进行了分析,根据沉降试验、颗粒试验和含水率试验结果,确定了砂砾石料填筑最优碾压施工参数。
On the experiment of concrete face rock fill dam gravel sand filling-rolling of Nazixia water power station of Datong river in Qinghai province,the site,the material and the layout are analyzed,according to the sedimentation experiment,grain experiment and moisture content rate experiment,the gravel sand filling optimal rolling construction parameters are decided.