摘要
以既有兰新线火石泉站站改工程为例,重点对区间信号机移设、既有道岔拆除、新增道岔纳入既有联锁,提出了安全、有效、经济的过渡方案,同时对新旧信号楼之间设备信息传输提出简单、可行的过渡方案,顺利完成本站的站场改造工程。实践证明,此方案安全可靠、使用简单、节省工程投资且减少对既有线运输的干扰,并对今后类似项目提供借鉴。
In this paper, the renovation project of existing Huoshiquan Station of Lanzhou-Xinjiang Railway is taken as an example. Focusing on removing the section signal devices, on dismantling the existing turnout, and on bringing the new turnout into the existing interlocking system, a safe, effective and economic transition scheme were proposed by the author. Meanwhile, a simple and feasible transition scheme for information transmission of devices between the old and the new signal buildings was also put forward. With these schemes, the renovation project of this station yard has been completed successfully. It has been found that, these schemes are safe, reliable, convenient to use, which can save project cost and can reduce the interference on the railway traffic as well as can provide reference for similar project in the future.
出处
《铁道标准设计》
北大核心
2013年第4期123-126,共4页
Railway Standard Design
关键词
铁路车站
联锁
信号过渡
方案
设计
railway station
interlocking
signaling transition
scheme
design