既有铁路车站站改信号过渡特殊处理 被引量:12

Special Treatment for Signaling Transition of Existing Railway Station Renovation Project
在线阅读 下载PDF
导出
摘要 以既有兰新线火石泉站站改工程为例,重点对区间信号机移设、既有道岔拆除、新增道岔纳入既有联锁,提出了安全、有效、经济的过渡方案,同时对新旧信号楼之间设备信息传输提出简单、可行的过渡方案,顺利完成本站的站场改造工程。实践证明,此方案安全可靠、使用简单、节省工程投资且减少对既有线运输的干扰,并对今后类似项目提供借鉴。 In this paper, the renovation project of existing Huoshiquan Station of Lanzhou-Xinjiang Railway is taken as an example. Focusing on removing the section signal devices, on dismantling the existing turnout, and on bringing the new turnout into the existing interlocking system, a safe, effective and economic transition scheme were proposed by the author. Meanwhile, a simple and feasible transition scheme for information transmission of devices between the old and the new signal buildings was also put forward. With these schemes, the renovation project of this station yard has been completed successfully. It has been found that, these schemes are safe, reliable, convenient to use, which can save project cost and can reduce the interference on the railway traffic as well as can provide reference for similar project in the future.
作者 王艳平
出处 《铁道标准设计》 北大核心 2013年第4期123-126,共4页 Railway Standard Design
关键词 铁路车站 联锁 信号过渡 方案 设计 railway station interlocking signaling transition scheme design
  • 相关文献

参考文献11

二级参考文献5

共引文献15

同被引文献79

引证文献12

二级引证文献60

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部