蜀河水电站工程二期混凝土施工导流水工模型试验研究 被引量:1

Study on Hydraulic Model Tests of River Diversion for Phase Ⅱ Concrete Construction,Shuhe Hydropower Station
在线阅读 下载PDF
导出
摘要 蜀河水电站厂房坝段混凝土施工采用已修建的右岸泄洪闸进行二期导流,需在厂房基坑上、下游修建横向挡水围堰。围堰方案确定前,分别对全年挡水围堰方案和汛期过水围堰方案过流情况进行了水工模型试验,根据模型试验结果确定了二期围堰最终方案为汛期过水围堰方案。 Transverse water-retaining cofferdams at both upstream and downstream of powerhouse foundation pit need to be built because the completed flood discharge gate on right bank is applied for Phase Ⅱ diversion so as to have dam sections at powerhouse of Shuhe Hy- dropower Station be concreted. Before determination of scheme for cofferdam, hydraulic model tests on flows are carried out respectively according to scheme for year-round water retaining cofferdam and scheme for overflow cofferdam in flood season. Based on the model test results, the final scheme for Phase Ⅱ cofferdam is the one for overflow cofferdam in flood season.
作者 王江涛
出处 《西北水电》 2012年第6期48-53,共6页 Northwest Hydropower
关键词 蜀河水电站 挡水围堰 汛期 过水围堰 水工模型 试验 Shuhe Hydropower Station water-retaining cofferdam flood season overflow cofferdam hydraulic model test
  • 相关文献

参考文献8

二级参考文献9

共引文献25

同被引文献6

引证文献1

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部