摘要
依据引汉济渭工程相关资料,结合受该工程影响的石泉、喜河、旬阳、蜀河各水电站的设计和运行资料,分析了该工程对各相关水电站入库径流量和年发电量的影响。结果表明:引汉济渭工程对各相关水电站年度入库径流量的影响与工程建设方测算的数据差别不大,但对各相关水电站年度发电量影响显著。
Based on relevant data on the project of water transmission from Hanjiang River to Weihe River and in consideration of information on design and operation of Shixuan, Xihe, Xunyang and Shuhe hydropower projects which are affected by the above-mentioned project, affects by the project on inflow runoff and annual power generation of the stations are analyzed. The analyzing results show that The annual inflow runoff of these stations affected by the project is not so different from that estimated by the Employer. But the project largely affects the annual power generation of these hydropower stations.
出处
《西北水电》
2012年第6期18-21,29,共5页
Northwest Hydropower
关键词
引汉济渭
发电量
耗水率
水能利用率
water transmission from Hanjiang River to Weihe River
power generation
water rate
hydroenergy utilization ratio.