灰土挤密桩在湿陷性黄土地区电厂冷却塔地基处理中的应用 被引量:11

Application of Lime Soil Piles in Collapsible Loess Foundation Treatment of Cooling Towers for Fossil-Fuelled Power Plants
原文传递
导出
摘要 火力发电厂冷却塔对地基的承载力要求较高,在天然地基承载力不能满足上部结构要求时,一般要采用人工方法对天然地基进行处理。本文通过工程实际,介绍了湿陷性黄土地区火力发电厂冷却塔地基处理工程中灰土挤密桩的设计、施工、检测,表明了灰土挤密桩在加固湿陷性黄土地区冷却塔地基工程中技术上是可行的,处理后的地基承载力和稳定性都得到了较大的提高。 The cooling tower for fossil-fuelled power plant has a high requirement for the ground bearing capacity. When the bearing capacity of natural foundation cannot meet the design requirement, a ground treatment usually can be taken to strengthen it. From the practical engineering, the design, construction, and detection of the lime soil pile to strengthen the collapsible loess ground are introduced in this paper. The results show that this method is feasible technically and can satisfy the requirement of collapsible loess ground, and the bearing capacity and stabilitv of the ground are raised greatly.
出处 《建筑科学》 北大核心 2013年第1期75-79,共5页 Building Science
关键词 湿陷性黄土 灰土挤密桩 冷却塔 地基处理 collapsible loess lime soil pile cooling tower ground treatment
  • 相关文献

参考文献7

二级参考文献4

  • 1杨鸿贵.地基处理手册(第二版)[M].北京:中国建筑工业出版社,2000.
  • 2中华人民共和国建设部.GB50007-2002建筑地基基础设计规范[S].北京:中国建筑工业出版社出版,2002.
  • 3中华人民共和国建设部.JGJ79-2002建筑地基处理技术规范[S].北京:中国建筑工业出版社,2002.
  • 4中华人民共和国建设部.GB50025-2004湿陷性黄土地区建筑规范[S].北京:中国建筑工业出版社,2004.

共引文献64

同被引文献104

引证文献11

二级引证文献50

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部