期刊文献+

厦门翔安海底隧道陆域浅埋段CRD法变形分配控制方法研究 被引量:2

Study on the Deformation Distribution Control of Tunneling with CRD Method in Landside Section of Xiamen-Xiang'an Subsea Tunnel
在线阅读 下载PDF
导出
摘要 基于变形分配理论、数值模拟和现场监测,研究了厦门翔安海底隧道两端陆域和浅滩地段大断面软弱地层浅埋暗挖CRD法施工变形机理,得到合理开挖顺序和变形分配控制标准,提出控制导坑封闭时间、导坑间距以及台阶长度等有效的变形控制措施,成功把施工变形控制在目标范围,避免发生超限变形和坍塌,大大提高施工进度,并确保了施工安全。研究成果和工程应用经验对后续类似工程有一定借鉴意义。 The total deformation of large cross-section tunnel is accumulated by stepped excavation,which is difficult to directly control. It must study the contribution of stepped excavation to the total deformation,so as to determine the control values of deformation of stepped excavation.Based on the deformation distribution control theory,numerical simulation and in-situ monitoring,the deformation mechanism of weak strata tunneling is researched in both ends of the landside section and shallows lot of Xiang'an Subsea Tunnel constructed with CRD method.Both the optimal excavation sequences(CRDl-3-2-4) and the deformation distribution control standard were formulated.The deformation control measures such as the closure time of the heading and the length of bench were given.Thus forming the shallow excavation CRD construction method in very weak strata of the subsea tunnel.Abnormal deformation was controlled effectively,and the tunnel deformation control target was achieved.Research is beneficial to the theory and practice,it has certain reference significance for the future similar engineering construction.
作者 王学斌
出处 《长江大学学报(自科版)(上旬)》 CAS 2012年第12期125-128,6,共4页 JOURNAL OF YANGTZE UNIVERSITY (NATURAL SCIENCE EDITION) SCI & ENG
基金 交通运输部行业联合科技攻关项目(2008-353-335-240)
关键词 海底隧道 CRD工法 软弱地层 变形分配控制方法 累积沉降 subsea tunnel CRD excavation method weak strata deformation distribution control theory accumulative settlement
  • 相关文献

参考文献4

二级参考文献12

共引文献75

同被引文献22

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部