超深临水基础后浇带预埋注浆管施工技术 被引量:5

CONSTRUCTION TECHNIQUE OF PRE-EMBEDDED GROUTING PIPE FOR POST-POURING BELT IN WATERFRONT SUPER-DEEP FOUNDATION
在线阅读 下载PDF
导出
摘要 中国人寿研发中心F-05地块(数据中心)工程四面环水,基槽最深部位达到了-23.400m,防水节点施工要求高,施工难度大。施工中在基础底板后浇带施工缝部位采用预埋全截面注浆管施工技术,较好地解决了因基坑体量大带来的地下室施工缝等薄弱环节防水质量控制难度大的问题,保证了地下室在后浇带部位的防水质量,同时提高了后浇带部位防渗漏应急补救能力,获得了较好的社会效益和经济效益。 China Life Center F-05 Block ( Data Center ) project is surrounded by water, the deepest part of trench reached -23.400 m, so the construction of waterproof node has high requirements and big difficulties. During construction, pre-embedded full section grouting pipe construction technique is adopted at construction joint of post-pouring belt on foundation bottom and difficulties in waterproof quality control at weak positions, such as construction joint at basement in big and deep foundation pit, are successfully solved to effectively ensure the waterproof quality at post-pouting belt position in basement. Meanwhile, emergency ability against leakage at post-pouring belt is improved and favorable social and economic benefits are obtained.
出处 《建筑技术》 2012年第11期974-976,共3页 Architecture Technology
关键词 超深基础 高水位 防水 后浇带 预埋注浆管 super-deep foundation high water level waterproof post-pouring belt pre-embedded grouting pipe
  • 相关文献

参考文献2

  • 1DB11/581--2008.轨道交通地下工程防水技术规程[S].
  • 2GB50208-2011,地下防水工程质量验收规范[S].

共引文献31

同被引文献27

引证文献5

二级引证文献43

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部