昆钢6号高炉(2000m^3)是我国第一座大量引进国外二手设备建成的现代化大型高炉,它综合采用了多项先进的新技术和新设备。由于开炉准备工作充分,开炉后高炉操作调剂得当,开炉后3个月就达到了设计生产能力。
The No. 6 BF (2 000 m3) at Kunming Iron & Steel Co was built with a lot of second-hand equipment introdued tron toreign. It adopted iron-making process and technological equipment. As a result qf abundant preparation and reasonable adjustment the BF has reached designed productive capacity three months after it was blown-in to Dec. 25 1998. It is the best level of domestic 2000 m3 BF from being blown-in to reaching designed productive capacity.