摘要 350km/h客运专线单线后张法单箱单室预应力混凝土简支箱梁属首次应用。为验证其各项指标,进行了4榀箱梁的试验工作。重点阐述了试验箱梁的工艺试验,包括箱梁预制、混凝土强度与弹性模量的发展变化、梁体混凝土水化热、试验箱梁预应力瞬时损失、终张拉预应力效果及弹性上拱度测试、预应力的传力长度及吊梁阶段测试结果。 ABSTRACT: The post-tensioned single-box & single-chamber prestressed concrete simply-supported box girder for 350 km/h dedicated passenger railway' s single-track line is used for the first time. To verify its performance indexes, the tests for four box-girders were carried out. This paper emphatically expounds the technological test for test box-girder including the prefabrication of box-girder, the development and change of concrete strength and elastic modulus, the hydration heat of girder-body concrete, the transient prestress loss of test box-girder, the effect of final tensioning prestress and the test for elastic camber, the transmission len^h of prestress and the test result nf hni.~tln~, ~t^m=
作者 任宏
出处 《科技情报开发与经济》 2012年第21期131-135,共5页 Sci-Tech Information Development & Economy
关键词 试验箱梁 工艺试验 合蚌客专 test box-girder technological test Hefei-Bangbu dedicated passenger railway
  • 相关文献

参考文献3

  • 1铁道部科学技术司.客运专线高性能混凝土暂行技术条件[S/OL].(2008—09-27).http://www.kmgzgs.com/show.asp?id=1418.
  • 2铁道科学研究院,铁道部产品质量监督检验中心,中铁工程设计咨询集团.客运专线预应力混凝土预制梁暂行技术条件[EB/OL].(2008-09-27).http://fdc.soufun.com/wenku/118693.html.
  • 3中国建筑科学研究院.JGJ/T10-95混凝土泵送施工技术规程[S/OL].[1995-10-01].http://wangjuan1979.blog.163.com/blog/static/3957737820l149104347332.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部