摘要 Hardfill坝是一种新坝型,有必要研究其结构破坏模式与破坏机理,评价结构安全度以促进新坝型的发展和应用。采用地质力学模型试验方法,进行了国内首次Hardfill坝破坏模型试验,分析大坝在外荷载作用下的变形、破坏特征及其演变过程。试验结果表明,Hardfill坝的破坏区域主要发生坝踵、坝趾及坝基面上,在超载过程中大坝经历了稳定、非线性变形以及失稳破坏3个阶段;大坝破坏模式为坝踵首先出现开裂,坝趾随即产生裂缝,最终坝体沿坝基面整体失稳,同时坝踵与坝趾附近部位开裂而形成了脱离坝体的三角形块体;坝踵、坝趾开裂超载系数K1=6.0~7.0,大变形超载系数K2=7.5~8.5,最终破坏超载系数K3=9.0~10.0。 Hardfill dam is a new type of dam.It is necessary to study the structure failure mode and mechanism,and also to estimate structure safety for promoting the development and application of the new dam type.Based on geomechnical model test,the first domestic failure model experiment of Hardfill dam was carried out to analyze the deformation and failure characteristics of the dam due to load.Results show that failure areas of typical Hardfill dam were located in dam heel,toe and the interface of the dam and foundation.During the overload process,the dam experienced three typical stages:stable,nonlinear deformation and failure.The failure mode was concluded as dam heel cracked firstly and then dam toe damaged,finally the dam integrally slid along the interface of the dam and foundation.Meanwhile,triangle blocks were separated from dam body resulted from the cracks in dam heel and toe;cracking overload safety K1 of dam heel and toe was 6.0 to 7.0,large deformation overload safety K2 was 7.5 to 8.5,and eventually failure overload safety K3 was 9.0 to 10.0.
出处 《水利学报》 EI CSCD 北大核心 2012年第10期1214-1222,共9页 Journal of Hydraulic Engineering
基金 国家自然科学基金资助项目(50679058) 四川大学水力学与山区河流开发保护国家重点实验室开放基金资助项目(0912) 武汉大学博士研究生科研自主基金资助项目(20082060201000021)
关键词 HARDFILL坝 结构破坏试验 破坏模式 超载安全度 Hardfill dam failure test failure mode overload safety
  • 相关文献

参考文献12

  • 1Londe P, Lino M . The faced symmetrical Hardfill dam: a new concept for RCC[J] . International Water Power & Dam Construction, 1992, 44(2) : 19-24.
  • 2贾金生,马锋玲,李新宇,陈祖坪.胶凝砂砾石坝材料特性研究及工程应用[J].水利学报,2006,37(5):578-582. 被引量:126
  • 3Stevens M A, Linard J. The safest dam [ J ] . Journal of Hydraulic Engineering, 2002, 128 (2) : 139-142 .
  • 4Peter J M. Hardfill and the ultimate dam[J] . Hydro Review Worldwide, 2004( 11 ) : 26-29.
  • 5Batmaz S. Cindere dam-107m high roller compacted Hardfill dam (RCHD) in Turkey [ C ]//Proceedings 4th Inter- national Symposium on Roller Compacted Concrete Dams. Madrid, 2003: 121-126.
  • 6Hirose T, Fujisawa T, Kawasaki H, et al. Design concept of trapezoid-shaped CSG dam [ C]//Proceedings 4th In- ternational Symposium on Roller Compacted Concrete Dams. Madrid, 2003: 457-464.
  • 7Mason P J, Hughes R A N , Molyneux J D . The design and construction of a faced symmetrical Hardfill dam[J] International Journal on Hydropower and Dams, 2008, 15 (3) : 90-94.
  • 8Tokmechi Z . Structural safety studies of Klahir dam in Iran [J] . Middle-East Journal of Scientific Research, 2010, 6(5): 500-504.
  • 9李永新,何蕴龙,乐治济.胶结砂砾石坝应力与稳定有限元分析[J].中国农村水利水电,2005(7):35-38. 被引量:14
  • 10杨令强,韩勇,陈祖坪.CSG坝渐进破坏过程分析[J].中国农村水利水电,2009(6):145-147. 被引量:6

二级参考文献49

共引文献138

同被引文献120

引证文献13

二级引证文献97

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部