摘要
介绍深圳赛格广场高层钢结构施工中 ,塔吊的选择、布置、安装、爬升、拆除等项内容。由于 2台塔吊均安装在核心筒以外的钢框架上 。
In the construction of high\|rise steel structure of Shenzhen Saiger Plaza, two tower cranes were installed on the steel frame outside the core barrel. This is the specialty of this work. Also the selection, layout, climbing and removal of tower crane are introduced in this article.
出处
《施工技术》
CAS
北大核心
2000年第8期38-40,共3页
Construction Technology
关键词
起重机械
附着式塔吊
内爬式塔吊
塔吊布置
安装
lifting equipment
attachment tower crane
internal climbing tower crane
layout of tower crane
installation
removal
high\|rise steel structure