摘要
论述了当前枢纽变电站无功补偿的现状及在第3绕组进行无功补偿存在的问题,提出了在主负荷侧直接安装无功补偿装置的必要性及重要意义;总结了110 kV电容器装置在唐山迁安220 kV变电站的挂网运行经验。
In this paper, the current situation of reactive power compensation of hub substation and the existed problem of the tertiary winding exisited during reactive power compensation are described. The necessity and significance of directly installing reactive power compensation device at main load side of substation are raised; and the operation experience of 110 kV capacitor bank in Tangshan Qianan 220 kV substation is summarized
出处
《电力电容器与无功补偿》
2012年第4期1-5,共5页
Power Capacitor & Reactive Power Compensation
关键词
枢纽变电站
主负荷侧
无功补偿
并联电容器
hub substation
main load side
reactive power compensation
shunt capacitor